Хлебные крошки

News

Commissioning were started

26.08.2016

Commissioning were started Commissioning were started.

See section "Ecology" http://zzcm.com.ua/en/ekologia


The heat insulation and installation of the filter are finished

05.08.2016

The heat insulation and installation of the filter are finished The heat insulation and installation of the filter are finished. Also the works for connection of control cabinet of the filter are completed.

See section "Ecology" http://zzcm.com.ua/en/ekologia 

Commissioning works for the operation of exhauste

29.07.2016

Commissioning works  for the operation of exhauste
The exhauster was connected to the exhaust duct. 
Commissioning works  for the operation of exhauster type DN 19 are in progress. 
Adjustment of exhauster with frequency control drive for different modes of  operation of exhauster are being done.

See section "Ecology" http://zzcm.com.ua/en/ekologia

Installation of new gas-cleaning equipment is being continued

22.07.2016

Installation of new gas-cleaning equipment is being continued The bundling of filter by exhaust ducts and filter heat insulation is in progress. Filter control cabinet connection is in progress.

See section "Ecology" http://zzcm.com.ua/en/ekologia
Installation of new gas-cleaning equipment is being continued

18.07.2016

Installation of new gas-cleaning equipment is being continued
At present moment following works are done:

1. Exhauster was assembled and installed on the base.
2. Filter heat insulation is in progress.
3. Filter control cabinet connection is in progress.

See section "Ecology" http://zzcm.com.ua/en/ekologia