Installation of new gas-cleaning equipment is being continued

18.07.2016

Installation of new gas-cleaning equipment is being continued
At present moment following works are done:

1. Exhauster was assembled and installed on the base.
2. Filter heat insulation is in progress.
3. Filter control cabinet connection is in progress.